The Launch Pad

Nothing starts half-ready: one step turns the signed deal into a scheduled job, the crew accepts the job and the pay on their phone, the subs bid and sign a purchase order for their stage, and the material order goes to the yard.

The operating system built exclusively for post-frame and barndominium builders.

Instead of: A week lost between signing and breaking ground, because the schedule, the crew, the subs and the order all start from a blank page.

Start project gate
Start Project
Zimmerman 40×72 Shop
The contract must be signed by both you and the customer before you can start this project.
Send the estimate, wait for approval and both signatures, then come back here.
Start Date
Sep 8, 2026
Assign Crew *
Crew B — Dale Whitmore
Project Address
418 Herr Ridge Rd, Nemaha, PA
Building Type
Commercial Shop
Build mode
Post-frameas alwaysBarndominiumadds the Trades section
Building Type Preset
Post frame
Stage Durations
Permitting14days
Dirt Work3days
Concrete5days
Materials Delivery5days
Framing8days
Post Set
Girts Done
Equipment on Site
Trusses Up
Bracing Complete
Framing Inspection
+ Add checkpoint
Siding / Roofing7days
Final Payment3days
45d
Total Duration
$128,400
Estimate Value
Nov 14
Projected End
CancelCreate Project
The real screen, drawn from the product’s own design system. Sample data — no customer information appears here.
Scroll — 10 steps
The short answer

What should barndominium preconstruction software do?

It should turn the signed contract into a scheduled job in one step: stages laid out from your own template, a crew that accepts the job and its pay on their phone, subs who bid and sign a purchase order for their stage, and a material order sent to the yard. Good barndominium preconstruction software then tracks each order until it arrives and is received line by line.

Why it works
  • Most barndominium delays come before the first concrete pour. One Texas builder puts design, engineering and permits at 6–14 weeks and lists septic, well, the electric co-op, the lender's appraisal and steel backlogs as pre-start hold-ups. Each runs on someone else's clock, so seeing them all in one place matters more than speed on any one. Texas Complete Barndo Solutions ↗
  • People underestimate how long their own work will take because they picture the plan, not their past. In Buehler, Griffin and Ross's studies, completion predictions were too optimistic, and the bias disappeared when people tied the estimate to relevant past experience. Stage templates built from how your jobs actually ran are that past experience. Buehler, Griffin & Ross, 1994 ↗
  • Subs need booking 6–12 weeks before they're needed, and booking further out than that makes return calls hard to get, says the Pole Barn Guru's construction-order guide. A bid request and a signed purchase order per stage pins each sub to his slot. Hansen Pole Buildings, 2026 ↗
  • Promises about pay that feel broken drive people out. In Robinson and Rousseau's study, 54.8% of employees reported their employer had violated the psychological contract, and violation was linked to turnover and lower trust. A crew that reads and signs its pay before the first post goes in has nothing to feel misled about. Robinson & Rousseau, 1994 ↗
Where it starts

One step, and the job is live on your board and on their link

Start Project won't run until the contract carries both signatures. Then it takes the Zimmerman 40×72 shop and asks only what's left: the start date, the crew, the building type. The stages lay themselves out with their durations, the projected end appears — 45 days, September 8 to November 14 — and the customer's link moves on from Agreement to Live Project without anyone sending them a thing. The customer feels the momentum the day they sign, and the office starts the job without starting from scratch.

Signed on Friday and started from a blank calendar on Monday is a week the customer notices.

Project progress
The real screen, drawn from the product’s own design system. Sample data — no customer information appears here.
Beat one

Your build order, ready-made for every building type

Each building type carries your stages, their durations and what counts as done. Dirt work, for one: strip topsoil, cut and fill to grade, compact the pad — done when the pad is within an inch across the footprint and the compaction ticket, 95% or better, is on the job. Built for the way a post-frame job really goes up, so a new job starts planned the way you build. Your PM stops rebuilding the same schedule every week.

A schedule rebuilt from memory for every job forgets a stage on the job that can least afford it.

Stage library editor
Building typePost frame ★ DefaultRenameDuplicate
ListMap6 of 7 stages linked
Permitting14days
Dirt Work3days
What this stage covers
Your crews see this.
Strip topsoil, cut and fill to grade, compact the pad. Done when the pad is within an inch across the footprint and the compaction ticket is on the job.
Grading CompletePad cut to grade and within an inch across the footprint.+ Needs another checkpoint first
Fill Material DeliveredWhat counts as done? (optional)+ Needs another checkpoint first
Compaction TestedTested at 95% or better — keep the ticket.Must be ticked firstDirt Work · Fill Material Delivered
Erosion Control in PlaceWhat counts as done? (optional)+ Needs another checkpoint first
+ Add Checkpoint
Concrete5days
Starts when Dirt Work is finished · Stops for rain, cold
Materials Delivery5days
Starts 2 working days before Concrete finishes (overlap)
Framing8days
Starts when Materials Delivery is finished · Stops for wind, lightning
Siding / Roofing7days
Starts when Framing is finished · Stops for rain, wind, lightning · 1 checkpoint first
Final Payment3days
Starts when Siding / Roofing is finished
The real screen, drawn from the product’s own design system. Sample data — no customer information appears here.
Beat two

A crew is a colour on the schedule, and time off books itself

Every crew has its colour across the build schedule, its leader and its men. Give a crew a date range and a reason — vacation, between projects, sick — and it goes inactive on the day and comes back at the end, with a notice each way. You only put a job on a crew that's actually free, and the crew's week off is respected without anyone having to remember.

A crew booked onto a job during the week they told you they'd be away is a crew that stops telling you.

Crew time off
Schedule Time Off
Reason
Start DateSep 7, 2026
End DateSep 11, 2026
5 days off — Sep 7 – Sep 11, 2026
The real screen, drawn from the product’s own design system. Sample data — no customer information appears here.
Beat three

The crew reads the job and the pay, then accepts it

Putting a crew on a job writes the acceptance for them. The crew lead opens it from the same link he clocks in on and reads the brief: the Wenger 40×60 shop, the phases his crew owns, September 8 to 19, the project manager's notes, and the $14,420 the crew stands to earn. He signs with a typed name and a drawn signature, and what he signed is frozen as it stood. Knowing the pay before the first post goes in is respect — and crews stay with builders who show it.

A job and a number agreed with a nod in the yard is an argument waiting for payday.

New project assignment
New project assignment
Wenger 40×60 Shop · Crew B
Your crew earns
$14,420.00
on successful completion of this project
Customer
Dwight & Ruth Hostetler
Address
1180 Mill Creek Rd, Bird-in-Hand
Building Type
40×60×16 Post-Frame Shop
Start
Sep 8, 2026
End
Sep 19, 2026
Phases your crew owns
1Site prep & layoutsitework2 days
2Posts & framingframing4 days
3Roof steelroofing2 days
4Siding & trimsiding3 days
View building plans
Notes from the project manager
Gravel pad is in and compacted. Overhead line runs along the north fence — keep the boom south of the posts. Owner wants the walk door on the east gable, not the plan side.
Accepting this project means your crew takes accountability for the phases above. You’ll sign to confirm, and the project manager will be notified immediately. If anything changes materially (dates, scope, payout), you’ll be asked to re-confirm.
DeclineAccept project
The real screen, drawn from the product’s own design system. Sample data — no customer information appears here.
Or

A no comes with a reason you can act on

Declining asks why, from a list rather than a blank box: the pay doesn't match the scope, a schedule clash, the site isn't ready, too far to travel. The office hears straight away, the job needs a new crew, and the reason sits on that crew's record beside every job it did accept. The crew gets a fair way to say no, and you find out why before it becomes a pattern.

A crew that just doesn't show up on Monday is the most expensive way to find out they never agreed.

Why are you declining?
Why are you declining?
Wenger 40×60 Shop · Crew B
Tell us why — this helps the project manager reassign or adjust. You can pick more than one.
Pay doesn’t match the scope of work
Schedule conflict with another project
Too many jobs back-to-back — need breathing room
Timeline too tight — need more prep time
Travel distance / commute too far
Equipment or tools not available for this build
Crew is already at full capacity
Scope is outside our current skill set or experience
Concerns about materials quality, gauge, or specs
Site access or safety concerns
Site prep or foundation isn’t ready
Weather or seasonal conditions
Concerns about the client (communication, expectations, history)
Need more project details before committing
Personal / family reason
Other (please specify below)
BackSubmit decline
The real screen, drawn from the product’s own design system. Sample data — no customer information appears here.
Beat four

Put a scope out to bid, and see the bids side by side

Write the scope once — the trade, the stage, when bids are due, the drawings — and invite two or more subs. Each gets a link with no login to send a price, a line breakdown, what he's leaving out and his own quote. The bids line up side by side, the lowest marked, each sub's insurance beside his name. Award one and it becomes a draft purchase order with that scope and that price; the others see they weren't picked. You compare like with like instead of three quotes in three formats, and the sub who lost knows where he stands.

Three quotes in three formats, each leaving out something different, compared on the back of an envelope.

New bid package
Bid package
New bid package
Title *
Electrical rough-in & service
Cost code / trade
Schedule stage
Bids due
Oct 7, 2026
Scope of work
200A underground service from the pole, main panel in the office, shop LED high-bays on two switch legs, receptacles every 12' on the sidewalls (GFCI where required), office and restroom circuits, two exterior wall packs and a 240V circuit for the unit heater. Permit and inspections by the electrician.
Drawings & attachments
Dawson Hoover - Floor Plan A-101 - Rev 1.pdfRemove
Add drawings or files
Invite subs
Send invites
CloseSave package
The New bid package window: title, cost code / trade, schedule stage, bids due date, the scope every bidder prices, and the drawings. Real screen · sample data.
Beat five

Every sub accepts a purchase order for his stage

A subcontract PO names the sub, the stage it pays for, the scope of work and its lines, each on a cost code. The moment it's sent it counts as committed cost on the job, by cost code. He accepts it from a link with no login — or declines it and says why, and it comes back to you to change — and he's paid against it as the work gets done: a percent complete, or the balance. The sub knows exactly what he agreed to, and you know what's committed before his bill arrives.

A sub's price agreed on the phone is a number nobody can find when his invoice comes in higher.

Dawson Hoover — Commercial Shop · Subcontracts
Subcontracts1 on insurance hold1 awaiting sub$42,450 committedBid packageSubcontract PO
PO-1018Part paidCornerstone Concrete Co.Insured$18,400
Concrete$9,200 paid · 50% billed
PO-1019Awaiting subValley Plumbing & DrainInsurance expired · pay on hold$9,250
Plumbing rough-in
PO-1020AcceptedSummit Electric LLCInsurance expiring$14,800
Electrical
Bid packages
Electrical rough-in & serviceAwarded2 of 2 bids in
Awarded to Summit Electric LLC · $14,800
Plumbing underground & rough-inAwarded2 of 3 bids in
Awarded to Valley Plumbing & Drain · $9,250
Committed by cost code
Cost codeSubsMaterialPaid
03 · Concrete$17,100—$8,550
06 · Framing—$41,280$20,640
10 · Plumbing$9,250——
11 · Electrical$14,800——
23 · Equipment rental$1,300—$650
The Subcontracts card in a project window, open: facts while closed (holds, POs awaiting the sub, committed), each subcontract PO with its stage, status, insurance badge and what's paid, the bid packages, and committed cost by cost code. Real screen · sample data.
Beat six

The order goes to the yard straight off the material list

The material list from the drawing becomes the order sheet — 34 lines, 1,247 pieces, from the purlins, girts and laminated posts down to the steel and trim — in the units the yard sells them. Pick the supplier, the delivery address and the week it's needed — the week of September 8 — add a note about access or staging, then send it or download it. Your yard gets a sheet it can quote without calling you, and your PM gets his evening back.

A lumber list retyped into an email is where a 16-footer becomes a 12-footer.

Supplier order sheet
Send Order
34 line items · 1,247 pieces · Ostrander — 40×60 Shouse
Close
Supplier
Ridgeview Building Supply
Send to
orders@ridgeview.demo.invalid
Deliver to
4180 Larkspur Road, Millbrook
Needed by
week of 8 Sep
Note to the supplier
Anything they need to know — access, staging, substitutions.
What the supplier receives
2x4 SPF · 16′88pcs
2x6 SPF · 8′4pcs
2x6 SPF · 10′9pcs
2x6 SPF · 16′92pcs
2x6 SPF · 20′6pcs
3 Ply 2x6 Lam. Post · 18′6pcs
3 Ply 2x6 Lam. Post · 20′20pcs
SYP 2x10 · 12′3pcs
Treated 2x8 · 20′10pcs
29Ga AG Panel · 11′67panels
29Ga AG Panel · 22′ 1″42panels
Ridge Cap 14″ Wide · cut to length60LF
Rake / Corner · cut to length144LF
Post-hole concrete5.8yd3
Send orderDownload CSVSent under your branding, and recorded on the supplier’s card.
The real screen, drawn from the product’s own design system. Sample data — no customer information appears here.
Beat seven

A purchase order that follows the delivery to the site

Every order becomes a purchase order on the job, with its payment terms, the date it was placed, the delivery expected, and a status that moves as the order does: sent, paid, on the way, arrived — or short and damaged, claim sent, settled. The office can answer “where's my steel?” in one look instead of three phone calls.

Orders that live in the yard's inbox and yours are orders nobody knows are late until the crew is standing around.

New Purchase Order
New Purchase Order
×
Supplier
Kessler Building Supply
Project (optional)
Hoover 40 × 60 Equipment Storage
PO Number
Auto-generated
Status
Draft
Payment Terms
Net 30
Date Placed
Aug 26, 2026
Expected Delivery
Sep 8, 2026
Line Items+ Add line
SKU
Description
Phase
Cost code
Unit
Qty
Unit $
Total
PT66-166x6 .60 CCA post · 16′Framing06 · Framingea3471.40$2,428
2X6-162x6 SPF #2 · 16′Framing06 · Framingea11814.85$1,752
PBR29-CH29ga PBR panel · Charcoal · 24′Roofing07 · Roofingea4668.20$3,137
—Trim screws · 1½″ · CharcoalRoofing07 · Roofingbox1242.00$504
Tax
469.27
Shipping / Freight
350.00
Subtotal$7,821
Tax$469
Shipping$350
Total$8,640
Notes (visible to supplier)
Will-call the posts Thursday; deliver the steel with the rest.
Internal Memo
Priced off the Aug quote — check the panel price before it goes.
CancelCreate PO
The real screen, drawn from the product’s own design system. Sample data — no customer information appears here.
Beat eight

Check it off the truck, short and damaged included

When it arrives, receive it line by line — ordered, received, missing, damaged — with a photo of what was wrong and what the supplier said: six wall girts short, the yard says Thursday; two split end to end. Everything arrived is one tap. What didn't becomes a credit claim or a reorder instead of an argument three weeks later. The crew's word about the delivery is on record, so nobody has to take the blame for a short load.

Six girts short, found when the crew reaches for them, is a day lost and a delivery charge.

Receive this order
PO-2026-0148Sent
Keystone Building Supply · due Sep 4, 2026
Everything arrivedSave what arrivedCancel
Ordered 180Received 172Missing 6Damaged 2Total $4,834.46
Framing2 lines
6x6-16’ CCA treated postea6X6-16-CCA24 × $46.80 = $1,123.20
Arrived
−24+
Missing
−0+
Damaged
−0+
2x6-16’ SYP wall girtea2X6-16-SYP96 × $12.40 = $1,190.40
Arrived
−88+
Missing
−6+
Damaged
−2+
6 short on the truck — yard says Thursday
2 girts split end to end
Add photophoto 1
The real screen, drawn from the product’s own design system. Sample data — no customer information appears here.
Every part of it, in detail
Start Project
The one deliberate action that turns a signed estimate into a live job with its stages, checkpoints and clocks running — built exclusively for post-frame and barndominium builders, where a signed contract becomes permits, dirt work and a slab date.
Stage templates by building type
Each building type gets its own stage list and dependency map — names, colours, lengths, checkpoints, what waits on what and the weather that stops each stage — editable by your company.
Order materials from your supplier
The take-off becomes an order sheet a yard can quote from — adjust what you already have, order what you're short, and receive it against the same list, with no second tool between the model and the yard.
An order sheet a yard can quote without calling you
The material list regrouped the way a supplier prices — one line per material and stock length, merged across every job it serves on the building.
Crew acceptance
Put a crew on a job and it has to say yes: your own men each tap Accept job on their phones, and a subcontractor crew's leader reads the brief and signs — or declines with a reason on the record.
Crews
Create crews, colour them, staff them, give them a leader — say whether each one frames or pours concrete, how it is paid, and see every job it is on from its card.
Bid packages: invite subs, level the bids, award one
Send one scope to several subs, let each price it from a link — one number or a breakdown, with their exclusions — compare the bids side by side, and award one into a subcontract PO. Exclusively post-frame and barndominium builders: the trades you bid out are the ones on your buildings.
Subcontract POs with cost codes and progress payments
A purchase order to a sub for a stage of the schedule: the scope in writing, priced lines with cost codes, the sub accepts from a link with their name, it counts as committed cost by trade, and you pay as the work gets done. The operating system built exclusively for post-frame and barndominium builders — so the PO hangs off the stages you already run the job by.
One customer link, no password
Your customer gets one link that opens as their estimate and later becomes their live project dashboard, with no account to create.
Barndominium full-trades schedule
A barndominium building type with every trade on its own stage — pad, utility trench, septic, under-slab plumbing, shell, rough-ins, spray foam, HVAC start-up — each tagged with its trade and the equipment it needs.
Budget & margin — job profit while it runs
The contract and every approved change, against each phase's budget, committed and actual cost — with the projected margin worked out while the job is still open. Made for post-frame and barndominium jobs, phase by phase.
Barndominium trades
Every trade on a barndominium job in one place — who does it, the price you agreed, the stages it covers and when they're on site.
THE SYSTEM, END TO END

Start one of your jobs
the day it's signed.

Nothing starts half-ready: one step turns the signed deal into a scheduled job, the crew accepts the job and the pay on their phone, the subs bid and sign a purchase order for their stage, and the material order goes to the yard. Thirty minutes with Keith, on one of your real structures — and the link we build is yours to keep whether or not you go any further.

leads2build.com
Laminated columns standing in a post-frame shell
Start project gate
Start Project
Zimmerman 40×72 Shop
The contract must be signed by both you and the customer before you can start this project.
Send the estimate, wait for approval and both signatures, then come back here.
Start Date
Sep 8, 2026
Assign Crew *
Crew B — Dale Whitmore
Project Address
418 Herr Ridge Rd, Nemaha, PA
Building Type
Commercial Shop
Build mode
Post-frameas alwaysBarndominiumadds the Trades section
Building Type Preset
Post frame
Stage Durations
Permitting14days
Dirt Work3days
Concrete5days
Materials Delivery5days
Framing8days
Post Set
Girts Done
Equipment on Site
Trusses Up
Bracing Complete
Framing Inspection
+ Add checkpoint
Siding / Roofing7days
Final Payment3days
45d
Total Duration
$128,400
Estimate Value
Nov 14
Projected End
CancelCreate Project